From Curiosity to Completion -
16 Months (Turn Key)
Week 1
- Tour our homes with a sales person
- Select a plan from our portfolio
- Plan overlay on homesite
- Define changes to plan
- Discuss construction financing options
Week 2
- Finalize home design and make any refinements needed
- Review proposal and included features
- Contract signing with deposit
Week 3-15
- Preliminary survey
- Preconstruction plans
Week 16-24
- Plan review (construction, materials, building survey, Builder Trend)
- Selections (exterior finishes and colors, cabinets, counter tops, flooring, fixtures,
electrical, low voltage, closet organizer, landscape architect – typically 3 days) - Submit for architectural review
- Permit applications
- Regulatory approvals
Week 25-26
- Homesite clearing
- Footers & foundation
Week 27-32
- Framing, roof, dry in
- Mechanicals – HVAC, electrical & plumbing
- Client walk through
Week 33-43
- Spray foam
- Drywall installation
- Cabinet, tile, finish carpentry
Week 44-60
- Paint
- Flooring
- Trim out
- Closet design & installation
- Landscaping & irrigation
- Clean
- New owner orientation
- Completion & close